week 8: half way?

Its week 8 now and we have only one floor to go, which means we are pretty much on schedule. Although I am told that once the 'wetwork' is done, the finishing takes quite some time.



They were plastering the ceiling, and Shafiq's cool glasses got all sement splattered.





To make a long and sad story short, the bathroom is 23 cm smaller than it should be, which is quite a disaster in an already small space. But what a nice view from my bath!